About the Project
This project will see repairs and upgrades to the lower/back parking lot at the Delaware Community Centre. The project plans include:
- Old asphalt removed, new drainage installed and new asphalt laid
- New access gates to lower parking lot
- New parking lot lines applied
- New concrete pad for garbage dumpster
- New pickleball court lines and new pickleball posts nets installed
SCHEDULE
Note this schedule may be affected by weather and other unforeseen circumstances.
- Effective Sunday, June 23, the parking lot will be closed for three weeks
- Contractors will be mobilizing on-site on Monday, June 24, to begin milling of the old asphalt
- Tentative reopening is July 12. Lot will be re-opened soon if the work is completed early.
Funding
- This project is funded through the Middlesex Centre capital budget. Projected costs are $158,500 for the new asphalt and sport court
and $36,200 for the security gate and installation. Information about Middlesex Centre's capital projects can be found on our Open Budget site.
QUESTIONS
Should you have any questions about this project, please contact Justin Fidler, Manager of Community Services.