Poplar Hill Park Washroom Improvements

Date

This project is now completed.


About the Project

This project will see the current washrooms at Poplar Hill Park renovated to meet accessibility standards under Accessibility for Ontarians with Disabilities Act (AODA). Renovations will include new automatic doors, fixtures, partitions, grab bars, change tables and counters.

Schedule

Construction is set to begin week of September 18, 2023, and continue throughout the fall, with an estimated completion date of December 20, 2023. Note this schedule may be affected by weather and other unforeseen circumstances.

The newly renovated washrooms will open to the public in May of 2024.

Alternative Washrooms During Closure

There are no alternative park washrooms available in Middlesex Centre as all are closing for the season.

Questions

Should you have any questions about this project, please contact Justin Filder, Manager of Community Services.

 

Thank-you for your patience and understanding while construction is underway.