Carriage Road Reconstruction

Date
Image
Road Closed Ahead Sign

Update:  PROJECT COMPLETED.  Thank-you to everyone for your patience as this work was underway.


Carriage Road is being reconstructed from Gideon Drive to approximately 800m south.

  • The work will involve rebuilding the road as well as the underground stormwater collection system and guiderails, from Gideon to the top of the hill. No bridge work planned. 
  • The work is planned to take place from May 16 to June 24 (subject to change based on weather, supply chain issues, and contractor availability).
  • Carriage Road will be closed between Gideon Drive and Harris Road from Wednesday, May, 18, 2022 at 7am until Friday, June 24, 2022, as part of this work.   

If you have questions about this project please contact Andrew Giesen, Transportation Manager.